FY18 - Municipal Services Center

Basic Project Information

Project Manager: Jabe Hunter

Managing Department:

Location:

Master Plan:

Financial Summary

Funding Source:

0%
of Cost Estimate
Committed

Cost Estimate: $1,718,091

Timeline

Current Start Date: 05/29/2018

Current Finish Date: 07/09/2018

Project Phase: Planning

Project Update

The Town has hired Little Diversified Architectural for the early planning and design phases of the project. An organizational structure for planning has been developed, a visioning session was held, and collaborative planning is underway. Programming for the facility is complete, and we are working toward selecting a site before we proceed to design. Once the site has been selected and acquired, the design of the facility can commence.