FY18 - Municipal Services Center
Basic Project Information
Project Manager: Jabe Hunter
Managing Department:
Location:
Master Plan:
Financial Summary
Funding Source:
0%
of Cost EstimateCommitted
Cost Estimate: $1,718,091
Timeline
Current Start Date: 05/29/2018
Current Finish Date: 07/09/2018
Project Phase: Planning
Project Update
The Town has hired Little Diversified Architectural for the early planning and design phases of the project. An organizational structure for planning has been developed, a visioning session was held, and collaborative planning is underway. Programming for the facility is complete, and we are working toward selecting a site before we proceed to design. Once the site has been selected and acquired, the design of the facility can commence.