FY18 - Streetscape Improvements - Graham St and Roberson St

Basic Project Information

This project includes Streetscape improvements along N. Graham Street and N. Roberson Street. The goal of the project is to increase pedestrian mobility and safety by promoting:  Accessibility: Creating predictable grade and width to create ADA accessibility;  Consistency: Completing connections between W. Franklin St. and W. Rosemary St. consistent with Rosemary St. and Downtown Streetscape Lighting and Master Plan; and  Safety: Accommodating future lighting improvements.

Project Manager: Megan Dale

Managing Department: Public Works

Location:

Master Plan: Downtown Streetscape Master Plan

Financial Summary

Funding Source: 2015 Streets & Sidewalks

0%
of Cost Estimate
Committed

Cost Estimate: $500,000

Timeline

Current Start Date: 02/08/2019

Current Finish Date: 03/21/2019

Project Phase: Planning

Project Update

Planning for this project is underway. Initial conversations with property owners are beginning to discuss interests.