FY18 - Estes Drive Bike & Ped Improvements (MLK to Caswell)

Basic Project Information

Project Manager: Bergen Watterson

Managing Department:

Location:

Master Plan:

Financial Summary

Funding Source:

0%
of Cost Estimate
Committed

Cost Estimate: $3,111,237

Timeline

Current Start Date: 05/29/2018

Current Finish Date: 06/15/2018

Project Phase: Design

Project Update

The Estes Drive design will be modified to eliminate improvements along the northern portion from MLK, Jr. Blvd. to Somerset Dr. due to future development along the road frontage. The developer for that area will be responsible for completing future roadway improvements. A supplemental agreement for Stewart to incorporate these design changes, along with some stormwater revisions, has been submitted to the Town and will need to be approved by NCDOT. The team continues to make progress on utility negotiations and right-of-way acquisition.