Project Project Manager Current Project Phase Cost Estimate
FY18 - Downtown Alleyway Improvements Sarah Poulton Bid $333,500
FY18 - Elliott Road Extension Bergen Watterson Planning $1,594,853
FY18 - Elliott Road Flood Storage Project Chris Roberts Design $240,497
FY18 - Ephesus Church Road Sidewalk Mike Wright Planning $1,111,660
FY18 - Estes Drive Bike & Ped Improvements (MLK to Caswell) Bergen Watterson Design $3,111,237
FY18 - Fire Station #1 Forrest Heath $100,000
FY18 - Friday Center Drive Reconstruction Mike Wright Construction $982,800
FY18 - Hargraves Community Center Roof Replacement Kevin Robinson Planning $336,215
FY18 - Hillsborough Street Reconstruction Greg Ling $775,000
FY18 - Homestead Road Sidewalk Mike Wright Planning $1,232,020
FY18 - Homestead Soccer Fields - ArtificialTurf Kevin Robinson Construction $236,530
FY18 - Morgan Creek Trail Phase 3 Bill Webster Acquisition $923,156
FY18 - Municipal Services Center Jabe Hunter Planning $1,718,091
FY18 - Northside Gym Roof Replacement Kevin Robinson Planning $113,000
FY18 - Old Durham Road Bergen Watterson Planning $1,574,664
FY18 - Seawell School Road (East) Sidewalk Mike Wright Planning $355,360
FY18 - Sidepath Along Fordham Bill Webster Design $236,600
FY18 - Streetscape Improvements - Graham St and Roberson St Megan Dale Planning $500,000
FY18 - Variable Message Sign System Kumar Neppalli Construction $1,046,714
FY18 - Wallace Deck Expansion Mike Wright Design #N/A
FY19 - Perry Creek Drive Culvert Repair Mike Wright #N/A